Main Client - Bio Products Laboratory, Elstree
Value: £3,100,000
Phase I WFI Completed December 2005: Included the installation of Steris Finn-Aqua 3000-S-7 Water For Injection still, with a ‘stand alone’ storage and distribution system. Two distribution loops supply 20 user points with WFI.
Phase II WFI Completed April 2005: Supplied as the first part of a complete system replacement for Building 27, with capacity for expansion for future distribution loops.
Phase III WFI Completed January 2007: The first of the WFI expansion phases. It is anticipated that two further phases of WFI will be required in the near future.
Phase II Purified Water Completed April 2005: Supplied as the first part of a complete system replacement for Building 27, with capacity for expansion for future distribution loops.
Phase III Purified Water Completed April 2006: The first of the Purified Water expansion phases.
Phase IV Purified Water Due Completion June 2007: The second of the Purified Water expansion phases.
Phase V Purified Water Due Completion January 2008: The third of the Purified Water expansion phases.
Services:
- Water For Injection (WFI) / Purified Water pipework
- Boroscopy inspection
- Passivation
- Insulation "GRP Hardclad"
- IQ/OQ documentation /validation
- Electrical power/controls/instrumentation
- Utilities service pipework
< back to Recent Projects
Site by: Dijit new Media